JaneCEM

Forum Replies Created

Viewing 1 post (of 1 total)
  • Author
    Posts
  • in reply to: Sunset dates
    JaneCEM #11890

    Sunset Date: Ferro Development Questions

    What has been the limiting factor in the sales process?

    • To maintain credibility in the market, the sales process has been stopped due to the delay in the commencement of the building process.

    Will marketing re-commence?
    • The marketing will re-commence once the final funding is in place and the building process has begun.

    Will the sunset dates of the sales be extended as a condition precedent to funding?
    • The Sunset dates have been extended to 2020 and 2021.

    Will there a be an initial QS report to verify the contract cost for GCB?

    • There will be a different builder to GCB – to be advised. The primary funder will require a QS report to be provided when the construction contract is available.

    Which bank is providing the Senior Debt?
    • The primary funder is Trilogy Funds Management Limited.

    There doesn’t seem to sufficient pre-sales to exit.
    • The sales have been halted at this stage, but the developer ensures that the sales will be completed once the marketing process starts again.

    Reply
Viewing 1 post (of 1 total)